[Nebula-users] Postponed (was: Nebula nodes unavailable 29 September)

Kent Engström kent at nsc.liu.se
Wed Sep 23 16:58:58 CEST 2020


Dear Nebula Users,

all the prerequisites for the test discussed below are not in place, so
it is cancelled.

That means that Nebula including compute nodes will be available as
usual on 29 September (we have removed the reservation of the nodes).

We'll get back to you when we know the new date for the test.

> we are currently replacing the UPS systems in the computer room where
> Nebula is located, and at the end of that we need to verify the
> performance. Tests have been scheduled on 29 September.
>
> To be able to achieve the correct power usage level for parts of the
> test, we need to be able to turn of the Nebula nodes. Therefore, we have
> reserved the Nebula nodes from 08:00 on 29 September. The nodes will be
> returned to service later that day when the tests have been concluded.
>
> Note:
>
> 1) The login node and the storage will be available during this time.
>
> 2) Jobs submitted in the week before the downtime need to have a
>    suitable TimeLimit ("-t" option) specified in order to start. If the
>    TimeLimit specified places the end time of a job beyond
>    2020-09-29T08:00 it will not be started until after the downtime.
>
> Best Regards,

-- 
Kent Engström, National Supercomputer Centre
kent at nsc.liu.se, +46 13 28 4444



More information about the Nebula-users mailing list